Gilbert Stream Pipeline Realignment
Pipelines

Gilbert Stream Realignment.
DN750 pipeline realignment
Steep sided and deep creek & gully crossing
13,000m3 cut and fill
54m long 2m diameter curved culvert
All pipeline bends fabricated off site
Complex construction process with machine winching required on most slopes
Short pipeline tie in window – required lots of planning
Full conceptual and detailed design
Construction and commissioning engineering support